Verifying Reinforcement

Ensure adequate rebar is placed horizontally and vertically as specified. This is typically every other course horizontally.

Vertical rebar is placed every 12-48″ as specified by local code and site specific engineering.

Add additional vertical rebar on each side of openings.

An example of rebar around an ICF door opening

Additional rebar around window and door openings.
Additional rebar around window and door openings.

You will also place lintel steel above doors, windows, or other larger openings as specified.

Rebar reinforcement in an ICF wall
Rebar reinforcement in an ICF wall