Basic ICF Installation Continuing Up the Wall Final Reinforcement & Specialty Blocks

Final Reinforcement and Specialty Blocks

Place vertical rebar after the top of the wall is reached or just before the last course is stacked. Always place vertical rebar before concrete is poured.

Verify wall height and note any specialty blocks required for the last course such as brickledge, taper top, half-height blocks (made from 1 BB block), etc.

Placing vertical rebar after the last course is placed
Placing vertical rebar after the last course is placed