Pouring an ICF Project Lessons Pouring an ICF Project Quiz

The Pouring an ICF Project quiz will cover some of the basic material presented in this lesson. Please answer the questions below. After completing the quiz you may mark this lesson complete and continue on to the next lesson.

Note: All quizzes in this course require an 80% passing grade to continue to the next lesson. If you do not meet the required score, click the “View Questions” button to see which questions were answered incorrectly and then click “Restart Quiz” to try again. 

Good luck!


When pouring in lifts around the structure, how high does BuildBlock recommend each lift to be poured?
Which is not a step of slumping?
What is the first thing you should do if blocks are delivered to your jobsite damaged?
Which of these is not a part of the pre-pour inspection phase?
For accuracy, how often does BuildBlock recommend performing a slump test?
BuildBlock recommends an aggregate of 3/8” (10mm) rock chip or river rock. If a larger aggregate is used (such as a ½” (12mm)) what should be done?
How many stages should the cone be filled with concrete when administering a slump test?
Which is a possible result of a slump test?

Check all that apply.
What is the recommended concrete slump to pour into an ICF wall?
What’s the best approach to pouring concrete into the ICF walls?