ICF Construction in 25 Steps Lessons Step 5: Vertical Rebar

Step 5: Vertical Rebar

Ensure that rebar is correctly set in the footing and extends properly above footings for non-contact laps in walls. The vertical dowels should extend beyond the top of the footing by at least 20 to 25 inches. That amount may be more depending on the lap requirements, as well as seismic and wind load ratings. Rebar inside concrete must be 3 inches from any soil exposure.

Step 5: Place vertical reinforcing as specified or per local codes and/or the BuildBlock Engineering Manual found at buildblock.com
Step 5: Place vertical reinforcing as specified or per local codes and/or the BuildBlock Engineering Manual found at buildblock.com