Penetration Sleeves
- The sleeve for a penetration should be constructed to the size required and no larger.
- Typically PVC pipe is used and placed through the ICF where required. The pipe should extend past the ICF several inches until the final wall is poured.
- Use spray foam adhesive around the sleeve on both sides to seal the sleeve in place and prevent any concrete leakage.
- Brace, strap and reinforce as necessary if multiple penetrations are located close to each other.
- Ensure proper concrete consolidation around all penetrations.