Other Pouring Considerations

  1. In multi-story structures, stop pouring concrete 8” down inside the form. This prevents a seam from being created at the point a new course of block is added.
  2. Protect the top interlock with tape or a metal track if continuing up the wall with another story.
  3. Place vertical rebar in the top course as specified to sufficient height for lap requirements.
Rebar extending past the first story in a multi-story structure
Rebar extending past the first story in a multi-story structure