Leveling Block
After 1-2 courses have been laid around the structure, shim and trim where necessary to level the block.
Once level, spot glue on both sides to keep the blocks in place (every 18-24” only). Once more block is stacked and alignment system is attached, a full bead of foam can be placed. Using too much foam adhesive at this time will lift the wall from level and create problems as you continue to stack block.