Jobsite Efficiency Tips
As you prepare your build, take time to plan out your process so that your jobsite can operate efficiently. Stage materials and bracing close to working areas or inside the project. Keep materials 6-feet back from the wall area to leave room for the bracing system when erected. Prep materials so they are ready to go before you need them. For example, it’s a good idea to stage your accessories and tools as well as pre-made bucking and pre-cut rebar.
Communication on the jobsite is very important. Use the surface of the ICF walls as a way to mark where certain items are going. Mark areas like vertical rebar locations, window centerlines, and rough opening sizes. Mark any special repeated block cuts on the wall so they are easy to repeat Agree on the method for marking and cutting blocks to avoid any waste. Locate and mark areas for penetrations, beam pockets, and blockouts.