Basic ICF Installation Pre Pour Inspection Footings Pre-Pour Inspection

Footings Pre-Pour Inspection

Ensure that proper rebar was placed in footings before they were poured and a footing inspection was performed if required.

Before stacking you should have verified that all vertical dowels are correctly placed with sufficient height above to footing to correctly lap vertical rebar in the walls.

Vertical rebar extending from footings
Vertical rebar extending from footings

Ensure that the walls match the layout that was marked on the footing before the wall was stacked.

Double check that walls meet specified dimensions and that the structure is square.

ICF walls stacked on a footing
ICF walls stacked on a footing